Work Breakdown Structure

The following figure shows the main activities of the project.

WBS code

Main Activity

Summary of activity

Practical Result

1000

Project Inception

Begin the formal execution of the programme:

·Mobilisation of Team as schedule arrival

·Initial visits / meetings as agreed with HCSO

·Brief review of current situation and development/ confirmation of the project plan for the project

·All tasks to be defined, scheduled and project plan (MS Project) created to manage the project

·Staff are operational and ready for work

·Review of current situation

·Detailed Plan with breakdown of all activities into tasks. Precise description, resource estimates and timing for each task input, output, and dependencies specified. (Project Inception report)

·Specification and agreement of the reporting and project management strategy

2000

System Design

Execution of the system design methodology to determine business needs, design software

·Business Analysis. Thorough review and analysis of the current map and agricultural related business processes of HCSO.

·Requirements Definition. Identification of all functions to be automated, identification of non functional requirements

·Conceptual Design, Use of CASE to prepare conceptual design of HCSO DM

·Technical Specification of upgrade and GIS server

·Specification, delivery , installation and acceptance testing of pilot/development systems as Task Description Forms

·Purchasing the upgrade of existing GIS

·DM designed according to business needs

·Data integration and migration designed

·Acceptance testing strategy and User Acceptance Test scripts ready for use.

·The existing GIS of HCSO is upgraded and provides sufficient platform for prototyping DM at next stage

3000

Compiling Map Collection Books

Complying a Map Collection Book

·Obtaining cadastral maps at 115 Land Offices

·Copying originals

·Compiling, photocopying/ printing and binding books

·Book containing collection of map extract of parcels involved in fruits and vineyard cultivation

4000

GIS Development

Build of DM system

·Order, install and commission the standard hw /sw incl. upgrade for HCSO

·Build of the design, establishment of prototype system, testing of functionality

·Data migration and integration

·Execution of the Acceptance Testing Plan for DM

·DM ready for acceptance testing

·Execution of acceptance test plan, and the software is accepted or referred for modification, in which case a subsequent test is applied.

5000

Implementation at HCSO

Make DM system operational (go live) at HCSO

·Design of detailed training programme and execution according to ToR.

·Install, test, make operational with DM system (software, database, manuals, etc.)

·Establish maintenance programme and Help Desk

·DM operates at HCSO

·Training programme implemented and staff trained

·Maintenance programme and support services are operational

6000

Project closure

Finishing the formal execution of project

·Evaluation of project

·Prepare and deliver final report

·With drawal project staff

Final Report

Summary / Overview of the Project Plan

Project control